Project

General

Profile

Activity

From 08/27/2014 to 09/25/2014

09/24/2014

06:33 AM Support #1297 (Resolved): Add current treatment unit to the Excel exportation
Oleksii Kurasov

09/17/2014

07:57 AM Feature #1294 (Resolved): Date validation for exams
For any exam, both exam's date and specimen date should be validated. Exam's date can't be in future, specimen date m... Oleksii Kurasov
04:54 AM Support #1293 (Resolved): New treatment protocols - compile diff list
New treatment protocols are approved. So, we should to find how to implement changes for eTB Manager. First step is t... Oleksii Kurasov
04:47 AM Support #1292 (Rejected): Create description for a virtual medicines varehouse for penntentiary
This description should be written based on the clear defined description of the current process Oleksii Kurasov
04:40 AM Support #1291 (Closed): Somethig went wrong for some Vinnytca cases. Exams don't open
Oleksii Kurasov

09/15/2014

06:36 AM Support #1279 (Closed): There are a lot of uncertaintlies for instant reports (the leftmost colum...
Selection formulas has been revised and corrected Oleksii Kurasov
06:06 AM Support #1253 (Closed): Package of some very useful tiny issues
Oleksii Kurasov
06:04 AM Support #1251 (In Progress): Prepare propositions about DOT implementation improvements. Need to ...
Waiting for new treatment protocols... Oleksii Kurasov
06:03 AM Support #1247 (Closed): Medicine order Kyiv Oblast Dispansery. Also, see attachment
The cause is double definition of a medicine in the common medicine dictionary Oleksii Kurasov
05:57 AM Support #1241 (Closed): Assist with installation of Internet connections for the National TB Inst...
Is it really closed? Oleksii Kurasov
05:55 AM Support #1235 (In Progress): eTBM software releases installation
Currently eTBManager updates are installed by UCDC system administrator Oleksii Kurasov
05:47 AM Support #1245 (Closed): All National TB institute users deleted by accident. Can we restore them ...
Oleksii Kurasov

09/01/2014

07:44 AM Support #1279 (Closed): There are a lot of uncertaintlies for instant reports (the leftmost colum...
These instant reports should be revised Oleksii Kurasov
07:15 AM Support #1278 (Closed): TB10 report. It is eternal question. How to calculate phase - by months o...
Some advanced users are confused. The clear answer is urgently needed. See example in Attachment Oleksii Kurasov
 

Also available in: Atom