Project

General

Profile

Bug #558

Correct the number of months displayed in the Cases on treatment tab in the new forecasting

Added by Luis Gustavo do Valle Bastos about 12 years ago. Updated about 12 years ago.

Status:
Closed
Priority:
High
Target version:
Start date:
04/01/2013
Due date:
04/10/2013
% Done:

80%


Description

Should be displayed the previous number of months related to the longer treatment included in the forecasting, starting from the month of the reference date. For example, reference date 28-March-2013 with treatment duration of 6 months, the system should display from March 2013 through September 2012.

See figure witht the current issue highlighted.

This issue is related with the bug # 557

Case on treatment issue.JPG (79.5 KB) Luis Gustavo do Valle Bastos, 04/01/2013 04:05 PM

140

History

#1 Updated by Oleksii Kurasov about 12 years ago

  • Due date set to 04/03/2013
  • Status changed from New to Resolved
  • Assignee changed from Oleksii Kurasov to Luis Gustavo do Valle Bastos
  • % Done changed from 0 to 100

Aligned to web version.

#2 Updated by Luis Gustavo do Valle Bastos about 12 years ago

  • Status changed from Resolved to Closed

Tested and adequate.

#3 Updated by Luis Gustavo do Valle Bastos about 12 years ago

  • Status changed from Closed to New
  • Assignee changed from Luis Gustavo do Valle Bastos to Oleksii Kurasov
  • % Done changed from 100 to 80

Given that in the desktop version all cases on treatment will default start treatment on the first day of the month they are assigned, please discard what was asked above and move back to the original logic, as follow. (sorry!!)

Should be displayed the exact previous number of months related to the longer treatment included in the forecasting, starting from the month of the reference date. For example, reference date 28-March-2013 with treatment duration of 6 months, the system should display from March 2013 through October 2012 (and not September 2012, as asked before).

Thanks!

#4 Updated by Oleksii Kurasov about 12 years ago

  • Due date changed from 04/03/2013 to 04/10/2013
  • Status changed from New to Resolved

#5 Updated by Oleksii Kurasov about 12 years ago

  • Assignee changed from Oleksii Kurasov to Luis Gustavo do Valle Bastos

#6 Updated by Luis Gustavo do Valle Bastos about 12 years ago

  • Status changed from Resolved to Closed

Tested and adequate.